skids said:
tjbnwi said:
If you go with the board longer than the door, make it end at the outside of the verticals. You need to put a Z flashing over the top of the kick board then install your side casing.
Tom
Ok thanks but doesn't that create essentially the same issue if I end at the outside vert of the brick molding I am adding to the jambs?
Sorry for the delay, for some reason I could not get on to FOG yesterday.
If your using a thicker vertical (brick mould), than the kick board, then I would end the kick board at the door edge, run the vertical past the kick board. If the vertical and kick board are the same thickness, bevel the kick board at 15º where the vertical will land on it, miter the vertical at 15º. Done this way the water will always run down hill. I've also padded out the kick board 1/4", it makes a nice detail with the bevel showing.
As long as you flash horizontal members properly, you should have no problems. A small piece of flashing with the leg bent up behind the vertical and over the top of the kick board with a small down lip will not cause any issues.
Tom