Michael Kellough said:[member=44099]Cheese[/member] those 300# trusses are going to span 28 ft? How tall are the trussss?
rvieceli said:Quickie question, this is a floating slab with a thickened edge? You don't need to go down below the frost line?
Cheese said:Well [member=71478]FestitaMakool[/member] , [member=3192]rvieceli[/member] , [member=167]neilc[/member] ...this is quite a home coming...this group hasn't been together in a while. [big grin]
They're dropping lumber on Friday and expect to have it framed up within a week. I asked about the trusses and they said they'd be set by hand...as in hand lifting the items into place. [eek] These beasts are 300# each...
I asked if they were going to use Lull lifts and they said that using that equipment within the city presented problems with power lines in the area so it was going to be all done by manual labor. Let's see how this plays out... [big grin] I also asked how many people would be needed to lift the trusses and they estimated 3 people per truss...so each worker will have to dead lift 100# each. This activity has suddenly become a sport for the younger athletes. [big grin]
I've erected trusses on a 50' barn in Wisconsin with a Lull lift and it was easy peasy. One person to operate the Lull and 2 people to spot the trusses.
FestitaMakool said:I’m pretty much in the same boat, finally started the restoration of my outhouse/shed.
It’s been me mostly alone, digging out soil floor [eek] jacking half the building up into former heights with hydraulic bottle jacks (I did dig out the bottom sills with a spade.. they once where 6x6” beams.. [huh])
Now after filling in 6 tonnes of gravel inside and outside, having poured 3 cubic meter of concrete delivered by a cement truck with hydraulic gutter all laid within 1 1/2 hour I leveled myself it’s a 322 sq feet (30sq m) of slab now.
It’s a fresh start. 10sq m of that is an extension. I’ve built the walls for the extension in modules (framing) and have now started to mount the wall modules to the concrete blocks. All the hard dirty work is now (nearly..) forgotten as it’s working with wood and as a framer (picky one [big grin] but I’m the only boss though!)
Looking forward to your progress Cheese, in before Christmas too you also? [wink]
Michael Kellough said:[member=44099]Cheese[/member] so there are two layers of 2” foam on top of gravel (or dirt?) then how thick is the concrete on top of the Pex/foam?
Cheese said:FestitaMakool said:I’m pretty much in the same boat, finally started the restoration of my outhouse/shed.
It’s been me mostly alone, digging out soil floor [eek] jacking half the building up into former heights with hydraulic bottle jacks (I did dig out the bottom sills with a spade.. they once where 6x6” beams.. [huh])
Now after filling in 6 tonnes of gravel inside and outside, having poured 3 cubic meter of concrete delivered by a cement truck with hydraulic gutter all laid within 1 1/2 hour I leveled myself it’s a 322 sq feet (30sq m) of slab now.
It’s a fresh start. 10sq m of that is an extension. I’ve built the walls for the extension in modules (framing) and have now started to mount the wall modules to the concrete blocks. All the hard dirty work is now (nearly..) forgotten as it’s working with wood and as a framer (picky one [big grin] but I’m the only boss though!)
Looking forward to your progress Cheese, in before Christmas too you also? [wink]
Well Festita...I'm pretty much in awe of what you're able to accomplish. I understand the bottle jacks but it's the "digging with the spade" thing that's over the top for me. Do they offer Dingos® for rent in Europe? That's what I used for installing a New York Bluestone patio about 18 years ago.
They're small walk-behind machines that are narrow enough to fit through a garden gate, they're tracked vehicles so they are light on their feet, and do an incredible amount of work on an incredibly small amount of fuel. I think the largest model is capable of hauling over a 1/2 ton of material. That would have made that 6 tonnes of gravel easy peasy. [smile]
I rented it for about 4 days and the fee was pretty reasonable considering the amount of work it can accomplish. I removed the top soil, hauled & spread the class 5, hauled & spread the sand and staged the pallets of bluestone while using about 4 gallons of gas.
Even though I was 20 years younger it was still a back saver and a time saver. Just something to consider for your next project. [big grin]
[attachimg=1]
Michael Kellough said:[member=44099]Cheese[/member] those 300# trusses are going to span 28 ft? How tall are the trussss?
Cheese said:So, I spent the day filling the cores of the cement blocks with foam. After laying down the 2 layers of 2" foam over the class 5 to receive the Pex tubing, I had a lot of extra large foam off-cuts and decided to put them to work. I cut HUNDREDS of 3" x 4-1/2" x 2" thick foam blocks that would fit into the block cores. The band saw was perfect to use for ripping these to the proper width while also cutting them for the proper length. Considering the number I cut, probably close to 400, it went extremely fast. Anyone who says they don't need a band saw is just whistling past the graveyard. [smile]
I put 3 pieces of foam in each core, spray foamed around each side, let it cure and then, spray foamed to fill any remaining cavity on the top. Let it cure and 2 days later I flushed each cavity up with a SAWZALL...what...did you say SAWZALL...remember that last Sawzall thread...and remember how many folks said they didn't need a Sawzall? Maybe this will be another introduction as to how handy this tool really is.
[attachimg=1]
[attachimg=2]
[attachimg=3]
[attachimg=4]
[attachimg=5
[attachimg=6]
Richard/RMW said:Hmmnnnn...
What I learned from my dad and his buddy Jim, 50+ years ago, was the proper filler for cement blocks was empty Coors cans...
Too much new fangled tech to absorb quickly.
rvieceli said:Cheese did you go with an attic truss or just a regular one?